🏗️ Cotulla High School Construction Update
We are pleased to report continued progress at the site of the new Cotulla High School!
Safety Update:
There are no safety concerns at this time. The contractor continues to maintain a clean and organized site. The perimeter fencing that was temporarily removed to accommodate summer work will be reinstalled at all construction areas prior to the start of the school year.
Site Work and Utilities:
Recent weather conditions have caused some delays to foundation progress; however, work continues. The existing water line beneath Building D has been successfully rerouted. Trench excavation for plumbing and electrical rough-ins is currently underway in Areas C and D. The foundation pour for Building E is tentatively scheduled for Tuesday, July 22.
Stay tuned for more updates!